Saetde, the company that manages the sector of Pas de la Casa-Grau Roig , has postponed the construction of the new chairlift of Pla de les Pedres that is located next to Bordes d'Envalira and Peretol freestyle area. The justification for this stoppage is due to the intense snowfall of recent days.
Likewise, Saetde does not have the environmental reports to be able to guarantee the start of works. And although the technicians of the Ministry are working on the subject and the report becomes possible before the end of the year, the workers will not be able to start the works since the snow prevents the works from being carried out in perfect conditions.
On the other hand, to this paralysis the common one of Canillo is added. According to El Periódico , Saetde has built a road in one of the lands of Canillo so the parish has sent a communication to the company where they are informed about the cutting of the road and urged to stop the works. In the same way, a sanction file has been opened to the company for an urban infringement . Will we see this new finish lift?
The Sierra Nevada National and Natural Park, the same that embraces the ski resort from which it takes its name, has been included in the IUCN 'Green List', which certifies that there can be coexistence between mountain and slopes.
and be the first to receive great ski deals!